Toto is painting the chainlink that nice dark blue.
 |
Extra insulation was put in many of the interior walls for
sound barrier. Like if you are making a lot of personal noise in the
bathroom, perhaps you don't want that amplified throughout the house...
|
 |
This insulation prevents all those "bedroom
noises" from escaping.
|
 |
And who wants to have to listen to the washing machine make a bunch of
noise? . |
All the insulation is complete and Andy the Building
Inspector gave us the go ahead for the next step.
 |
Then the drywall was delivered!
Toto went ahead and painted the living room beams.
|
 |
We attacked the ceiling drywall with much enthusiasm.
Measure twice, cut once... yeah right. |
 |
New toys time!
I got this nifty magazine attachment for a screw gun. This blasts
drywall screws in as fast as you can push the nose to the drywall. Killer
time saver. |
 |
Bedroom #2 has all its ceiling drywall up. |
 |
The closets' ceilings are up. |
 |
The front room ceiling wasn't too hard to put up. |
 |
Here it is done. |
 |
The boyz did a great job.
Hey watch where you point that thing, Manny! |
 |
Meanwhile Paco is still dealing with the windows... |
 |
And removing tape... |
 |
And painting the window sills... |
 |
And we are getting the front entryway cleaned up. |
Go back to week 1 at Casa de las
Ratas
Week 2: more cleanup and
roof replacement.
Week 3: the big dumpster
comes and the hot mop boys will show up.
Week 4: fixing the valleys, new kitchen subfloor
Week 5: prepping the roof, framing in the kitchen, ripping out more
floors...
Week 6: Replacing a ridge board, new tiles on the roof, more paint, why not?...
Week 7: Let's get the roof finished! And destroy more stuff inside!
Week 8 & 9: Final touches on roof, removing all the old hard conduit/black pipe,
filling yet another roll-off dumpster.
Week 10 & 11: Rough plumbing finished, electrical
started, more tools acquired, and a big header installed
Week 12: Kill that old rear bathroom,
level the yard, cast some concrete.
Week 13: More electrical work, HVAC installation finished, get ready for
drywall.
Week 19: More painting to brighten up the Rat House. More window prep.
Week 22: Big Inspection goes well, stucco scratch
coats, wiring beauty shots
Week 23: Is that The Rat House or Circus Vargas? Termite Tenting! Nuke
'em all.
Insulation begins.
Week 24: Itch Itch Scratch Scratch Insulation
Coming up next week at Casa de las Ratas
Week 32: Drywall and yet more drywall.
Week 34: MORE drywall!
Week 38: 8,000 drywall screws
later, it's all up. Mud and tape brigade begins!
Everything up to week 52: Bath and
Floor Tile installation.
Week 62: Windows Reinstalled. I
hope you are not afraid of COLOR!
Week 64:
Finish color washing. Install some crown moulding.
Week 66: Tons of cool details to
show off. Moulding, AC Grilles, Floor Tile, Medicine cabinet...
Week 67: Window casings
Week 76: Copper Gutters! Too cool. Exotic lights
start arriving.
3/3/2005: Outside lights and
wood floors installed!
6/29/2005:
Kitchen Cabinets installation!
Rat House 2007
Rat
House floor plan PDF