Casa de las Ratas Week 19

up to June 8, 2002

Time to treat the neighborhood to the Rat House's first paint job in probably 30 years...

Scotty joined the rat crew to help out with the painting. Here he is making the patio look nice.

 

 

All I could say all day was "WOW." 

 

 

Manny and Martin have been hunting down termite infestations and replacing affected wood. This section is in the second bedroom.

 

Toto and Paco are still stripping and sanding down all the windows. They are about done now and will start on stripping all the window frames and sills.

 

The only window sill that the termites had really gotten to was in the third bedroom. Manny and I replaced this one today. It was easy to make a new one with its angled cuts on the table saw.

 

Piece o' cake.

 

 

 

 

 Manny closed up that extra kitchen window. The stove will go there and I don't want a window over the stove.

 

 

 

 Go back to week 1 at Casa de las Ratas

Week 2: more cleanup and roof replacement.

Week 3: the big dumpster comes and the hot mop boys will show up. 

Week 4: fixing the valleys, new kitchen subfloor

Week 5: prepping the roof, framing in the kitchen, ripping out more floors...

Week 6: Replacing a ridge board, new tiles on the roof, more paint, why not?...

Week 7: Let's get the roof finished! And destroy more stuff inside!

Week 8 & 9: Final touches on roof, removing all the old hard conduit/black pipe, filling yet another roll-off dumpster.

Week 10 & 11: Rough plumbing finished, electrical started, more tools acquired, and a big header installed

Week 12: Kill that old rear bathroom, level the yard, cast some concrete.

Week 13: More electrical work, HVAC installation finished, get ready for drywall.

Coming up next week at Casa de las Ratas 

Week 22: Big Inspection goes well, stucco scratch coats, wiring beauty shots

Week 23: Is that The Rat House or Circus Vargas? Termite Tenting! Nuke 'em all. Insulation begins.

Week 24: R-19 in all the ceilings.

Week 28: The guys will complete all the wall insulation. Drywall Begins!

Week 32: Drywall and yet more drywall.

Week 34: MORE drywall!

Week 38: 8,000 drywall screws later, it's all up. Mud and tape brigade begins!

Everything up to week 52: Bath and Floor Tile installation.

Week 62: Windows Reinstalled. I hope you are not afraid of COLOR!

Week 64: Finish color washing. Install some crown moulding.

Week 66: Tons of cool details to show off. Moulding, AC Grilles, Floor Tile, Medicine cabinet...

Week 67: Window casings

Week 76: Copper Gutters! Too cool. Exotic lights start arriving.

3/3/2005: Outside lights and wood floors installed!

6/29/2005: Kitchen Cabinets installation!