The HVAC FAU has been hung and ducting is being run.
|
![]() |
There is the new 4-ton FAU hung neatly from the floor
joists.
|
![]() |
The exhaust for the furnace has been nicely located in the wall cavity between the shower and bedroom #2. |
![]() |
The return duct for the AC has been installed in the hall ceiling. |
![]() |
This return duct runs through the 1st bedroom closet. Now
that it has been located, we are reclaiming the wasted area that used to
be a basement go-down access, back when the house had a basement in Santa
Monica. Now that the house only has a crawlspace, we do not need a full
door to get into the crawlspace.
Here, Manny and Martin are installing two cinder blocks to match the rest of the foundation.
|
|
The new sill plate was anchored to the cinder block supports with 1/2" anchor bolts and floor joists were installed for a new closet/alcove for the 1st bedroom. I'll probably leave this as an open alcove, perfect for a TV and sound system, and make a round arch feature out of it. The wall was opened up and a header installed. 1 x 6 sub-floor sheathing was put on and finally the erstwhile basement door was closed up.
|
![]() |
Ricardo was busy outside painting the rafter tails. |
![]() |
![]() |
While Toto began the window repair assembly line. |
![]() |
These windows are not in too bad shape. After stripping and sanding off the 3 layers of old paint, they will fine. I had gotten a quote for new windows for the whole house. It would have been $23,000. We will be repairing the old windows which suit the character of the house much better anyway. |
Go back to week 1 at Casa de las Ratas
Week 2: more cleanup and roof replacement.
Week 3: the big dumpster
comes and the hot mop boys will show up.
Week 4: fixing the valleys, new kitchen subfloor
Week 5: prepping the roof, framing in the kitchen, ripping out more floors...
Week 6: Replacing a ridge board, new tiles on the roof, more paint, why not?...
Week 7: Let's get the roof finished! And destroy more stuff inside!
Week 12: Kill that old rear bathroom, level the yard, cast some concrete.
Coming up next week at Casa de las Ratas
Week 19: Sanding windows, drywall blocking, paint the house exterior!
Week 22: Big Inspection goes well, stucco scratch coats, wiring beauty shots
Week 23: Is that The Rat House or Circus Vargas? Termite Tenting! Nuke 'em all. Insulation begins.
Week 24: R-19 in all the ceilings.
Week 28: The guys will complete all the wall insulation. Drywall Begins!
Week 32: Drywall and yet more drywall.
Week 38: 8,000 drywall screws later, it's all up. Mud and tape brigade begins!
Everything up to week 52: Bath and Floor Tile installation.
Week 62: Windows Reinstalled. I hope you are not afraid of COLOR!
Week 64: Finish color washing. Install some crown moulding.
Week 66: Tons of cool details to show off. Moulding, AC Grilles, Floor Tile, Medicine cabinet...
Week 76: Copper Gutters! Too cool. Exotic lights start arriving.
3/3/2005: Outside lights and wood floors installed!